A Ks with B to build him a house for $100,000. A builds the whole house according to specifications except

A Ks with B to build him a house for $100,000. A builds the whole house according to specifications except

Question:

A Ks with B to build him a house for $100,000. A builds the whole house according to specifications except for one window in the bathroom which is too small. B refuses to pay the purchase price. A sues B.a. Has B’s duty to pay been triggered by A’s performance? Must B accept and pay for the house?b. Has A completely discharged his contractual obligations?c. What will the result be? Why?

Expert Answer:

Answer rating: 100% (QA)

a B s duty to pay has not been triggered by A s performance because A did not fully perform according to the contract specifications A built the house
View the full answer